08.07.2025
TEBOLVL: First machine tests a succes
As the TEBOLVL plant construction site enters its final phase before commissioning at the end of 2025, here is a progress report on the various phases to date.

Curretn state of progress
Initially scheduled, the symbolic “out of water/out of air” stage has been reached, enabling the finishing work to be completed, such as the passageways for the various flows and the fittings around the future production line. The availability of the finished frame has enabled the first machine tests to be successfully launched, particularly on the conveyor side. The final stage involves the assembly of the unwinding unit, which has just been delivered to the site. The production line will now be ready for final adjustments and the first TEBOLVL production tests. Outside, the imposing structure of the boiler for the steaming process is being completed, so that the first tests can begin shortly.
The construction of the offices
The construction of the future offices and common areas will make extensive use of wood. This choice means that users can enjoy a comfortable working environment and high thermal performance in both the hot summers and sometimes harsh winters typical of the region. The construction principle is based on timber-framed walls combined with floors and ceilings.
LVL load-bearing panels. The XXL format of the panels, 8m long and 1.80m wide, means that this structural element can be installed quickly and to a high standard. The exterior cladding will be made of Douglas fir cladding with a contemporary design. The structure will be completed by mid-July, when the finishing work begins. The teams will then be able to move in at the start of the new academic year.

THE SURROUNDINGS OF THE PLANT
Particular attention is being paid to the exterior of the site. Roadworks have begun and will make it easier and safer to travel between the various parts of the plant. Work is continuing on the planting of trees in the immediate vicinity of the production site. The basins have been completed and are now receiving topsoil.
LVL
ARRIVAL OF THE LAST CONTAINER
The container containing the decoiler components has arrived. Symbolically, it is the last container to enter the factory. In a few weeks’ time, the containers will leave in the other direction for international customers. They will be carrying TEBOLVL® produced at the Lempdes- sur-Alagnon plant. The construction adventure will be over. Now it’s time to focus on the quality and sustainable production of a biosourced, agile building material.